CNIC Completes Servicing of TRIDENT XIV
After
eleven (11) months of comprehensive life extension
works, the jack-up, TRIDENT XIV left CNIC’s repairs site
at Berth 4 in Douala on Sunday, 18th November
2007 following completion of servicing.
Commenced on 4th
January 2007, the life enhancement works comprised:
-
Grit blasting of tanks for
a surface area of 17 000mē
-
Grit blasting and painting
of haul over a surface area of 8000mē
-
Replacement of 700 tons of
steel
-
Heavy lifting of the rig
on the Fjjel Fairmount Barge to enable elaborate repairs
of the Spud Cans
-
Piping and electrical
works as well as painting of legs.
|